Uploaded image for project: 'CFA MX '
  1. CFA MX
  2. CFAMX-16163

Testing CLONE 2021.R6 Sprint 3 - Daily Sales Roll Back - Automatic Option

    Details

    • Type: Story
    • Status: Closed (View Workflow)
    • Resolution: Done
    • Affects Version/s: None
    • Fix Version/s: CFA 2021R6
    • Component/s: None
    • Labels:
      None
    • SCRUM Team:
      Great White
    • Story Points:
      3
    • Work Type Classification:
      Sustaining

      Description

      Story

      As a user, I would like the system to automatically determine if a new Workflow exists that I need to finalize even if the "Daily Sales" task is marked as "Complete".

      Acceptance Criteria

      1. When the "Daily Sales" task is marked as "Complete", the system should re-poll the database to check for Workflow days that may have been created and are unfinalized for the month in question.
      2. If a new Workflow exists that needs to be finalized by the user, the "Daily Sales" task should go from the "Complete" state to the "Review Task" state. From here, the page follows the current functionality and displays all workflow days that need to be finalized for the month.
      3. When the End of Month has been marked, the Daily Sales task is always marked as Complete. We do not need to continue polling in this case.

        Attachments

          Issue Links

          There are no Sub-Tasks for this issue.

            Activity

              People

              • Assignee:
                charles.wheeler Charles Wheeler
                Reporter:
                jason.powell Jason Powell
              • Watchers:
                2 Start watching this issue

                Dates

                • Created:
                  Updated:
                  Resolved:

                  Time Tracking

                  Estimated:
                  Original Estimate - 6.5h
                  6.5h
                  Remaining:
                  Remaining Estimate - 0h
                  0h
                  Logged:
                  Time Spent - 6h Time Not Required
                  6h

                    PagerDuty

                    Error rendering 'com.pagerduty.jira-server-plugin:PagerDuty'. Please contact your Jira administrators.