Uploaded image for project: 'CFA MX '
  1. CFA MX
  2. CFAMX-1632

Spike - Offsite Sales > Offsite Address Validation Phase

    Details

    • Sprint:
      CFAMX 2019R2 Sprint 2
    • SCRUM Team:
      Brotherhood of Mutants
    • SOW (Time Tracking) Project:
      44918
    • Work Type Classification:
      Sustaining

      Description

      Story
      As a developer, I would like to understand the integration work needed between SmartyStreets and InFORM.

      Notes
      In order for address validation to be implemented for Offsite Sales Locations, a research task is needed.

        Attachments

          Issue Links

          There are no Sub-Tasks for this issue.

            Activity

              People

              • Assignee:
                neha.shah Neha Shah (Inactive)
                Reporter:
                staten.putnal Staten Putnal (Inactive)
              • Watchers:
                0 Start watching this issue

                Dates

                • Created:
                  Updated:

                  Time Tracking

                  Estimated:
                  Original Estimate - 21h Original Estimate - 21h
                  21h
                  Remaining:
                  Time Spent - 29.5h Remaining Estimate - 52h 32m
                  52h 32m
                  Logged:
                  Time Spent - 29.5h Remaining Estimate - 52h 32m
                  29.5h

                    PagerDuty

                    Error rendering 'com.pagerduty.jira-server-plugin:PagerDuty'. Please contact your Jira administrators.