Uploaded image for project: 'CFA MX '
  1. CFA MX
  2. CFAMX-16585

Testing-Sprint-6-2021.R6 : Finalize Workflow Day Via Script - Daily Sales

    Details

    • Type: Story
    • Status: Closed (View Workflow)
    • Resolution: Done
    • Affects Version/s: None
    • Fix Version/s: None
    • Component/s: None
    • Labels:
      None
    • SCRUM Team:
      Great White
    • Story Points:
      3
    • Work Type Classification:
      Sustaining

      Description

      Story

      As an admin, I would like workflow days finalized by the "Finalize Workflow - Closed Business Days" script to not show up in the "Daily Sales" section of End of Month.

      Details

      This script should mark days as Finalized. This means the operator at the location should not have to interact with workflow days finalized by the script at all including making sure these days do not show up in the Daily Sales section of End of Month.

      Acceptance Criteria

      Confirm for dates that have been finalized via the "Finalize Workflow - Closed Business Days" help desk script:

      1. These finalized workflow days do not populate the "Daily Sales" section of End of Month.

        Attachments

          Issue Links

          1.
          Create Test Scripts QA Task Done Unassigned

          0%

          Original Estimate - 0.5h
          Time Not Required
          2.
          Review Test Scripts QA Task Done Unassigned

          0%

          Original Estimate - 0.5h
          Time Not Required
          3.
          Deploy QA Task Done Unassigned

          0%

          Original Estimate - 0.5h
          Time Not Required
          4.
          Execute Test Cases QA Task Done Unassigned

          0%

          Original Estimate - 0.5h
          Time Not Required
          5.
          Functional Review with QA Dev Task Done Unassigned

          0%

          Original Estimate - 0.5h
          Time Not Required
          6.
          DIT Dev Task Done Unassigned

          0%

          Original Estimate - 0.5h
          Time Not Required
          7.
          Design Review Dev Task Done Unassigned

          0%

          Original Estimate - 0.5h
          Time Not Required
          8.
          Story Documentation Dev Task Done Unassigned

          0%

          Original Estimate - 0.5h
          Time Not Required
          9.
          Testing in Testing QA Task Done Charles Wheeler

          100%

          Original Estimate - 1h
          Time Spent - 1h
          10.
          Testing in Staging QA Task Done Charles Wheeler

          100%

          Original Estimate - 1h Original Estimate - 1h
          Time Spent - 2h

            Activity

              People

              • Assignee:
                charles.wheeler Charles Wheeler
                Reporter:
                jason.powell Jason Powell
              • Watchers:
                0 Start watching this issue

                Dates

                • Created:
                  Updated:
                  Resolved:

                  Time Tracking

                  Estimated:
                  Original Estimate - 6h
                  6h
                  Remaining:
                  Remaining Estimate - 0h
                  0h
                  Logged:
                  Time Spent - 3h Time Not Required
                  3h