Uploaded image for project: 'CFA MX '
  1. CFA MX
  2. CFAMX-4669

CFA - When viewing the tool for days on hand, the display shows a negative value

    Details

      Description

      The issue seems to occur when correcting a negative on hand, to a positive on hand, using the Correct On Hand function.

      • Navigate to a SO store and go to  Create Order
      • Store used 01580
      • Add order - ( Used MBM)
      • Locate and item that shows a RED negative on hand quantity. 
      • Navigate to correct On Hand
      • Correct On hand to a positive number. 
      • Save
      • Navigate back to Suggested Details panel, click on On hand "i" icon. 
      • The days on hand show in the screen shot, - 12.09
        • With a forecasted usage of 2.66. The Days on hand should be something like 5.63 days
           
      • * Popover to show:
        • Days On Hand: x.xx days
        • Where x.xx = Days On Hand = Stock On Hand / Daily Usage
          • Days On Hand = Stock On Hand / Daily Usage
          • Where
          • Daily Usage = Forecasted usage / Number of Days
          • Number of Days = Cover until date - date created - Days that are marked as Closed
          • For example: Mon 22nd April 13:00 - Friday 19th April 06:00 - Sunday 21st April = 2.29 days
          • Days that are marked as Closed - We are using this, rather than Sundays, so as to exclude other days that have a forecast but will not have any usage (Site closed for rebuild, Christmas day, Thanksgiving, etc).

       

       

       

        Attachments

        1. image-2019-06-20-13-07-43-933.png
          151 kB
          Sandy Sweeney
        2. image-2019-06-24-09-42-11-970.png
          168 kB
          Gareth Leibbrandt
        3. image-2019-06-24-09-42-20-350.png
          147 kB
          Gareth Leibbrandt

          Issue Links

            Activity

              People

              • Assignee:
                Gareth.Leibbrandt Gareth Leibbrandt (Inactive)
                Reporter:
                sandy.sweeney Sandy Sweeney (Inactive)
              • Watchers:
                1 Start watching this issue

                Dates

                • Created:
                  Updated:
                  Resolved:

                  Time Tracking

                  Estimated:
                  Original Estimate - 8h Original Estimate - 8h
                  8h
                  Remaining:
                  Time Spent - 6h Remaining Estimate - 2.5h
                  2.5h
                  Logged:
                  Time Spent - 6h Remaining Estimate - 2.5h
                  6h

                    PagerDuty

                    Error rendering 'com.pagerduty.jira-server-plugin:PagerDuty'. Please contact your Jira administrators.