Type: Story
-
Status: Closed (View Workflow)
-
Resolution: Done
-
Affects Version/s: None
-
Fix Version/s: None
-
Component/s: None
-
Labels:None
-
Sprint:2022.R3 New Features Sprint 2
-
SCRUM Team:Brotherhood of Mutants
-
Story Points:2
-
Work Type Classification:Sustaining
Details
AC
- When a day is finalized that the TBC's can be viewed for that day
- When a day is finalized and the TBC's have been refunded, the are not listed on the CDS Export
- When a day is finalized that TBC's cannot be edited
- A TBC that comes in after finalize day with missing information will be editable New
- Once this TBC is set, make this TBC uneditable because the day was already Finalized
- After all TBCs are assigned for that day, then fire the export (ie. re-raise the banking close event)
- *The only exception being those that are received after the day is finalized.
- It is possible to navigate between previously finalized days using the date control
- implements
-
CFAMX-12484 InFORM Angular Technology Update
- In Development
There are no Sub-Tasks for this issue.