      Description

      As an operator, I want to be notified that an item has negative on hand so that I can count it before applying the count

      Notes

      • Negative on hand values should not be displayed in the Suggested Count mode
      • The user should have a visual indication that the item needs to be counted
      • It should NOT be possible to Apply the count if there are items that have a negative on hand
      • Mockup

      Acceptance Criteria

      1. Confirm that the quantity is populated for items that have a negative system on hand
      2. Confirm that the cell is highlighted in red to indicate that the on hand value is negative
        • This tells the user that the item need to be counted
      3. Confirm that the only option under the Actions button is Delete when there is an item that has a negative on hand
        • Similar to entering a value that exceeds the max
      4. Confirm when all items have a counted value equal to or greater then zero, other options become available under Actions
      5. Confirm that items that have a positive on hand do not require any action

        Attachments

        1. SuggestedCount.png
          SuggestedCount.png
          72 kB
        2. screenshot-1.png
          screenshot-1.png
          24 kB
        3. RegularCount.png
          RegularCount.png
          83 kB
        4. RedCells.png
          RedCells.png
          82 kB
        5. CorrectOnHand.png
          CorrectOnHand.png
          28 kB
        6. BlankFields.png
          BlankFields.png
          71 kB

          Issue Links

            Activity

              People

              • Assignee:
                will.englefield Will Englefield (Inactive)
                Reporter:
                will.englefield Will Englefield (Inactive)
              • Watchers:
                0 Start watching this issue

                Dates

                • Created:
                  Updated:
                  Resolved:

                  Time Tracking

                  Estimated:
                  Original Estimate - 20h 40m
                  20h 40m
                  Remaining:
                  Time Spent - 18.5h Remaining Estimate - 2h
                  2h
                  Logged:
                  Time Spent - 18.5h Remaining Estimate - 2h Time Not Required
                  18.5h

                    PagerDuty